10/1/2005 to 9/30/2006
| Activity Summary |
| Scouting: | 33 |
| Trail Maintenance (PCT): | 292 |
| Training: | 119 |
| Total Volunteer Hours: | 444 |
| Activity Detail (most recent on top) |
| Project Date: | 9/9/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Trail maintenance. AmeriCorps related. |
Volunteers |
Hours |
| Linde, Tom | 4 |
| Project Total: 4 |
| Project Date: | 8/31/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Brice Hammack |
| Location: | Crest Camp to Panther Creek |
| Description: | Scouting for AmeriCorps project. |
Volunteers |
Hours |
| Hammack, Brice | 8 |
| Linde, Tom | 7 |
| Project Total: 15 |
| Project Date: | 7/11/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Jim Webb |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Log out |
Volunteers |
Hours |
| Webb, Jim | 5 |
| Project Total: 5 |
| Project Date: | 7/10/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Jim Webb |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Log out |
Volunteers |
Hours |
| Webb, Jim | 5 |
| Webb, Paul | 5 |
| Project Total: 10 |
| Project Date: | 7/8/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Trout Creek north |
| Description: | Cleared 1 tree (18"). Installed new culvert and repaired 40' of tread. |
Volunteers |
Hours |
| Linde, Tom | 6 |
| Palodieltuk, John | 3 |
| Palodieltuk, Wanda | 3 |
| Project Total: 12 |
| Project Date: | 7/7/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Trout Creek north |
| Description: | Cleaned 14 drain dips, brushed and repaired tread on 1.2 miles of trail. |
Volunteers |
Hours |
| Linde, Tom | 9 |
| Project Total: 9 |
| Project Date: | 6/29/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Brice Hammack |
| Location: | Crest Camp to Carpenters Lake Trail Junction |
| Description: | Scouting |
Volunteers |
Hours |
| Hammack, Brice | 21 |
| Project Total: 21 |
| Project Date: | 6/27/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Steve Queen |
| Location: | Crosscut Training at Wind River Training Center |
| Description: | 2 volunteers participated in crosscut training. |
Volunteers |
Hours |
| Allen, Eric | 19 |
| Cobb, Roberta | 10 |
| Owen, Kim | 19 |
| Project Total: 48 |
| Project Date: | 6/13/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Road 6808 to Panther Creek |
| Description: | Cleared 2 trees, repaired root wad damage. |
Volunteers |
Hours |
| Johnson, Gary | 7 |
| Linde, Tom | 9 |
| Project Total: 16 |
| Project Date: | 6/1/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Larry McLaughlin |
| Location: | Road 2070 to Road 2090 |
| Description: | Cleared a few trees, cleaned drain dips and a little brushing. |
Volunteers |
Hours |
| McLaughlin, Larry | 10 |
| Project Total: 10 |
| Project Date: | 5/24/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Larry McLaughlin |
| Location: | Road 2070 to Sedum Trail Junction |
| Description: | Cleared 26 trees, repaired 80 drain dips, 10 water bars, 2 slides, 3 root wads, brushing on 4 miles, short bits of tread repair. |
Volunteers |
Hours |
| Allen, Eric | 12 |
| Doty, Pat | 12 |
| Hammack, Brice | 12 |
| McLaughlin, Larry | 12 |
| Vetter, Dick | 12 |
| Webb, Jim | 12 |
| Project Total: 72 |
| Project Date: | 5/21/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Trout Creek north |
| Description: | Logged out three threes, repaired 10' of tread. |
Volunteers |
Hours |
| Johnson, Gary | 4 |
| Linde, Tom | 4 |
| Project Total: 8 |
| Project Date: | 5/15/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Jim Webb |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Log out |
Volunteers |
Hours |
| Mooney, John | 7 |
| Webb, Jim | 7 |
| Project Total: 14 |
| Project Date: | 4/26/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Jim Webb |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Drainage and rock work. |
Volunteers |
Hours |
| Webb, Jim | 7 |
| Project Total: 7 |
| Project Date: | 4/5/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Wind River crossing |
| Description: | Bridge site visit and design ofr replacmeent. Getting estimates for materials. Picking up supplies for bridge. Turnpike visit and design for repairs and getting estimates. |
Volunteers |
Hours |
| Linde, Tom | 8 |
| Project Total: 8 |
| Project Date: | 4/5/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Brice Hammack |
| Location: | Panther Creek to Trout Creek |
| Description: | Removed 18 trees. Cleaned drain dips and water bars. Light brushing and tread repai. |
Volunteers |
Hours |
| Doty, Pat | 10 |
| Hammack, Brice | 10 |
| Jones, Larry | 9 |
| Mooney, John | 10 |
| Murphy, Des | 10 |
| Vetter, Dick | 10 |
| Project Total: 59 |
| Project Date: | 3/29/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Brice Hammack |
| Location: | Trout Creek |
| Description: | Removed rotted bridge. |
Volunteers |
Hours |
| Doty, Pat | 7 |
| Gibson, Bus | 7 |
| Hammack, Brice | 7 |
| Vetter, Dick | 7 |
| Project Total: 28 |
| Project Date: | 3/23/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Jim Webb |
| Location: | Trout Creek to Sedum Ridge |
| Description: | Scouting |
Volunteers |
Hours |
| Webb, Jim | 7 |
| Project Total: 7 |
| Project Date: | 3/18/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Steve Queen |
| Location: | Chainsaw Certification (Wind River Ranger Station) |
| Description: | 12 volunteers participated in a chainsaw re-certification course at the Wind River Ranger Station. |
Volunteers |
Hours |
| Carter, Patty | 6 |
| Cobb, Roberta | 6 |
| Doty, Pat | 6 |
| Goodwin, Ron | 6 |
| Hammack, Brice | 6 |
| Konner, Jack | 6 |
| Latiolais, Paul | 6 |
| Linde, Tom | 5 |
| Martiny, Chuck | 6 |
| McLaughlin, Larry | 6 |
| Queen, Steve | 6 |
| Vhay, John | 6 |
| Project Total: 71 |
| Project Date: | 2/27/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Wind River Bridge |
| Description: | Logged on a 44" cottonwood. |
Volunteers |
Hours |
| Hutton, Warren | 3 |
| Linde, Tom | 3 |
| Project Total: 6 |
| Project Date: | 2/16/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Road 6800020 North |
| Description: | Brushing limbs off trail. |
Volunteers |
Hours |
| Linde, Tom | 7 |
| Project Total: 7 |
| Project Date: | 1/6/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Panther Creek area |
| Description: | Cleared trail of moveable blow down and limbs. Repaired 2 drainage problems and fixed bridge approach. |
Volunteers |
Hours |
| Linde, Tom | 4 |
| Project Total: 4 |
| Project Date: | 1/1/2006 |
| District: | Mount Adams Ranger District |
| Leader: | Tom Linde |
| Location: | Wind River Bridge to Panther Creek |
| Description: | Evaluated repair needs of Wind River bridge decking. Scout 4 miles north of Panther Creek. |
Volunteers |
Hours |
| Linde, Tom | 3 |
| Project Total: 3 |