Volunteer Projects — Pacific Crest Trail Association
Wind River Ranger District
10/1/2002 to 9/30/2003
| Activity Summary |
| Trail Maintenance (PCT): | 124 |
| Training: | 80 |
| Total Volunteer Hours: | 204 |
| Activity Detail (most recent on top) |
| Project Date: | 5/14/2003 |
| District: | Wind River Ranger District |
| Leader: | Brice Hammack |
| Location: | Sedum Ridge to Trout Creek |
| Description: | Removed 12 trees with axe and handsaw, repaired all drainage dips, miscellaneous brushing and tread repair. |
Volunteers |
Hours |
| Doty, Pat | 10 |
| Hammack, Brice | 10 |
| McLaughlin, Larry | 10 |
| Vetter, Dick | 10 |
| Webb, Jim | 10 |
| Project Total: 50 |
| Project Date: | 5/2/2003 |
| District: | Wind River Ranger District |
| Leader: | Brice Hammack |
| Location: | Panther Creek to Carpenters Lake Trail Jct. |
| Description: | Scouted (5/2 to 5/3). |
Volunteers |
Hours |
| Hammack, Brice | 21 |
| Project Total: 21 |
| Project Date: | 4/16/2003 |
| District: | Wind River Ranger District |
| Leader: | Larry McLaughlin |
| Location: | Road 2000 toward Sedum Ridge |
| Description: | Logged out 12 trees between 3" and 16", cleaned six water bars and repaired two instances of slide damage. Misc brushing and tread repair. |
Volunteers |
Hours |
| Doty, Pat | 11 |
| Hammack, Brice | 11 |
| McLaughlin, Larry | 11 |
| Vetter, Dick | 11 |
| Webb, Jim | 9 |
| Project Total: 53 |
| Project Date: | 3/22/2003 |
| District: | Wind River Ranger District |
| Leader: | Steve Queen |
| Location: | Wind River Ranger Station (Chainsaw Certification) |
| Description: | Eight volunteers participated in a chainsaw re-certification course with the Wind River Ranger District. |
Volunteers |
Hours |
| Cobb, Roberta | 8 |
| Doty, Pat | 8 |
| Goodwin, Ron | 8 |
| Hammack, Brice | 8 |
| Konner, Jack | 8 |
| Lukins, Dick | 8 |
| Martiny, Chuck | 8 |
| McLaughlin, Larry | 8 |
| Walker, Richard | 8 |
| Webb, Jim | 8 |
| Project Total: 80 |